Terminal 3 Heathrow

Terminal 3 Heathrow

Location: Heathrow, London (circa. 2017)
Design Brief: Walkway Balustrades, Internal Glass Partitioning, and Stair Structure Design
CAD System: AutoCad Advance Steel

There are few places where your work will be viewed by tens of thousands on a day to day basis. Heathrow airport is one of those places. It was my absolute pleasure to be involved with this project.

During the revitalisation of T3 I was tasked with the production drawings for the Stair Structure and Glass Balustrade Systems. As well as the various support structures throughout the project. We were to incorporate the original 2-D parts details as utilised in T2 into the new details, so that the continuity of design would flow from one terminal to the next.

Whilst the part details would remain, there was still a lot of design required around the interfaces of existing elements such as the hanging supports for the retail sector which needed to fit around existing HVAC and main structure. The new stair structures and balustrades which needed to interface with the new escalators. Not to mention the glass partitions and monitor displays that were fitted to cambered beams, requiring adaptive mounts.

Overall this was a challenging project with a rewarding outcome.

Spirit of Cornwall – Chelsea Flower Show

Spirit of Cornwall – Chelsea Flower Show

Location: Chelsea Flower Show, London (circa. 2018)
Design Brief: Spirit of Cornwall Exhibition
CAD System: AutoCad Advance Steel

I was presented with a unique opportunity to be sole designer of the metalworks for the Spirit of Cornwall exhibit at the 2017 Chelsea Flower Show.

The main structure was supported by a flat bar lattice frame on either side, together with walkway sections and fence panels, of the same theme.

The way that it had been visually designed by the architect, whatever fixing methods we used needed to be flush and near invisible to the eye. We couldn’t have any protruding bolt heads or threads which presented a challenge of how it should all be bolted together. Not only that, the exhibit needed to be deconstructed into multiple sections.

The solution was that the spacer tubes that run between the flat bar structure should be internally threaded and we would use a combination of countersunk bolts and threaded studs.

By strategically placing the tube spacers, we were able to form a structure that was demountable and moved to its permanent home in Cornwall after the show had ended.

During fabrication, the dish itself had to be spun by a specialist metalworks company, and when we received it, at first measure, it appeared to be within specs. But once the fabricator started putting all the pieces together things just weren’t matching up.

With the fabricator at a loss for what was wrong I had to go out into the workshop and figure out what was going on for myself. As it turned out that although the overall diameter of the dome was correct they had actually spun it to the wrong radius this meant that it was about 100mm too deep at the apex.

After some recalculating we came up with a method for joining all that back together without compromising the overall scheme of the dome piece.

There were a couple of interesting features incorporated into the design. The outlet for the waterfall needed to be precisely level, so I designed a tilting outlet.

Once the structure was installed and water was introduced into the feature whoever was installing had the ability to fine tune the water pour without needing to re-level the entire structure.

There was also the fear of the waterproofing of the feature leaking inside the dome. With all the shifting around it was a real concern.

We had to have a lifting eye in the centre of the dome whilst at the workshop to be able to lift and manoeuvre the structure during fabrication. My suggestion was to permanently weld the nut on the inside of the dome and to make a removable plug that could be periodically removed incase of water ingress.

Both are simple solutions that make a difference to the end product installation and future maintenance.

Kidbrooke Village

Kidbrooke Village

Location: Kidbrooke, London (circa. 2019)
Design Brief: Phase 3 / Block D Metalwork Package
CAD System: AutoCad Advance Steel

Kidbrooke is part of a broader residential redevelopment strategy undertaken by Berkeley Construction in South East London. For the Third Phase Block D section of this project I was tasked as the lead metalwork designer and with further design coordination.



The redevelopment comprised five main residential buildings of varying height which share a communal green space on a raised podium. At street level there are a number of generous retail spaces. 

My role was to fully expand design on the balustrades at the podium level (metal and glass); the main entrances to apartment blocks; retail space canopies; car park and BoH metalworks including the automated gates as well as any other miscellaneous metal works that could fall under our scope of works as the project progressed. Simultaneously ensuring the design was harmonious within this project and previous phases.

The Substation doors were easily one of the biggest design challenges. The subcontractor responsible for substation louvre doors wasn’t able to manufacture the doors or the system because it was just too big, the structure was way outside the scope of what any louvre company could provide.

The door needed to be robust and secure (SR2), but like any other substation it needed to facilitate removal of the UKPN transformers for maintenance. To solve this issue I proposed incorporating a hybrid approach.

The main structure would be adapted to normally be bolt fixed in it’s closed position with louvre panels set into the frame work. During maintenance they could unbolt the doors around the perimeter and they would swing open through 180 degrees to allow unimpeded access to the substation.

By incorporating hidden proprietary hinges arranged in a unique way, meant that all areas were able to meet strict ‘secure by design’ criteria whilst also meeting the UKPN maintenance requirements. A clear win for everyone.